Regional & rural roads

Macleay Valley Way regional road work

Each week Council's dedicated roads crews carry out a huge amount of work. 

Below is an update on the work delivered last week and scheduled on our regional and rural local roads network for the week commencing Monday 27 September.

Regional Roads - Construction, Rehabilitation and Maintenance

 LAST WEEK THIS WEEK
Plummers Lane, Clybucca- Rehabilitation Plummers Lane, Clybucca- Rehabilitation
Line marking Line marking
Deferred To commence
Point Plomer Road, Crescent Head - Southern Section - Contractor Point Plomer Road, Crescent Head - Southern Section - Contractor
Spreading and compacting of basecourse Spreading and compacting of basecourse
40% complete To continue
Crescent Head Road, Crescent Head
Sealing
Complete
Armidale Road, Yarravel (Link Road - Ferrier Drive) Armidale Road, Yarravel (Link Road - Ferrier Drive)
Pegging out of site Pegging out of site
60% complete To continue
Placement of silt fencing Placement of silt fencing
60% complete To continue
Placement of drainage Placement of drainage
80% complete To continue
Widening of pavement Widening of pavement
70% complete To continue
Placement of sub base Placement of sub base
50% complete To continue
Armidale Road, Willawarrin
Heavy patching to commence

 

Rural Local Roads – Construction, Rehabilitation & Maintenance

Works to be programmed in the new financial year.

Urban Local Roads – Construction, Rehabilitation & Maintenance

Works to be programmed in the new financial year.