Bridge infrastructure

Each week Council's dedicated roads crews carry out a huge amount of work. 

Below is an update on the work delivered last week and scheduled on our bridges, wharves and jetties for the week commencing Monday 20 March 2023.

Bridge replacement program

 LAST WEEK THIS WEEK
McKintyres Bridge, Upper Smiths Creek Road, Kundabung McKintyres Bridge, Upper Smiths Creek Road, Kundabung
Installation of side track
Complete
Installation of box culverts Installation of box culverts
Deferred To commence
Latters Bridge, Carrai Road, Carrai Latters Bridge, Carrai Road, Carrai
Installation of new decking units Installation of new decking units
50% complete To complete
Chain O Ponds Bridge, Chain O Ponds Road, Collombatti Chain O Ponds Bridge, Chain O Ponds Road, Collombatti
Installation of headstocks and abutments Installation of headstocks and abutments
Deferred To commence
Installation of new decking units
To commence
Frogmore Bridge, Old Station Road, Frogmore
Dismantling of existing bridge
Deferred to 11/4/23
Installation of base slabs
Deferred to 11/4/23
Medica Bridge, Upper Smiths Creek Road, Kundabung (Contractor)
Bridge approach works
Complete
Removal of side track
Complete
Demobilising of site
Complete

 

Timber bridge refurbishment program

Works currently in planning. To be delivered at a later date.

Wharves, jetties and footbridges program

Works currently in planning. To be delivered at a later date.