Bridge infrastructure
Each week Council's dedicated roads crews carry out a huge amount of work.
Below is an update on the work delivered last week and scheduled on our bridges, wharves and jetties for the week commencing Monday 20 March 2023.
Bridge replacement program
LAST WEEK |
THIS WEEK |
McKintyres Bridge, Upper Smiths Creek Road, Kundabung |
McKintyres Bridge, Upper Smiths Creek Road, Kundabung |
Installation of side track |
|
Complete |
|
Installation of box culverts |
Installation of box culverts |
Deferred |
To commence |
Latters Bridge, Carrai Road, Carrai |
Latters Bridge, Carrai Road, Carrai |
Installation of new decking units |
Installation of new decking units |
50% complete |
To complete |
Chain O Ponds Bridge, Chain O Ponds Road, Collombatti |
Chain O Ponds Bridge, Chain O Ponds Road, Collombatti |
Installation of headstocks and abutments |
Installation of headstocks and abutments |
Deferred |
To commence |
|
Installation of new decking units |
|
To commence |
Frogmore Bridge, Old Station Road, Frogmore |
|
Dismantling of existing bridge |
|
Deferred to 11/4/23 |
|
Installation of base slabs |
|
Deferred to 11/4/23 |
|
Medica Bridge, Upper Smiths Creek Road, Kundabung (Contractor) |
|
Bridge approach works |
|
Complete |
|
Removal of side track |
|
Complete |
|
Demobilising of site |
|
Complete |
|
Timber bridge refurbishment program
Works currently in planning. To be delivered at a later date.
Wharves, jetties and footbridges program
Works currently in planning. To be delivered at a later date.